Saturday 28 May 2011

Our journey so far.....

Here is where our build is at:

     Initial Deposit   7/09/2010
     Soil Report    29/09/2010    
     Contour Survey   5/10/2010 
     Tender Appointment   17/12/2010    
     Tender Signed   21/02/2011    
     Building Contract Appointment   4/03/2011    
     Building Contract Signed   8/03/2011    
     Permit Ordered   29/03/2011    
     Permit Received   6/05/2011    
     Colour Selection   25/03/2011    
     Electrical Selection   20/04/2011     
     Kitchen Upgrades   12/04/2011    
     Water Board Approval   17/03/2011    
     BASIX Approval   16/03/2011    
     Construction Certificate   6/05/2011    
     Engineering Drawings Signed   25/03/2011    
     Finance Approval   12/05/2011    
     Land Settlement   17/12/2010    
     Construction Drawings Signed   24/05/2011   
Survey request ordered on Friday 20 May 2011, still waiting to see some pegs on our block, fingers crossed this happens early next week.

Monday 23 May 2011

Our Madison 36 Plans

Here is our Madison 36 floorplan with some modifications to suit what we wanted in the house (walk in pantry, storage and bath to ensuite).

First Floor Plan


Ground Floor Plan


West Elevation

Sunday 22 May 2011

Our block in Kellyville Ridge

Here is our little patch of dirt in Kellyville Ridge, it's nearing 12 months since we put our initial deposit on our block and in that time we have sold our home of nearly 8 years, moved into a rental property (and already been here for 6 months) considered selling our block and buying an existing home (when it all got too difficult) and committed to building with Eden Brae Homes the Madison 36 design.


Here is a shot of our frontage


Here are some shots of our future views (will be great from our master balcony!)