Saturday, 5 November 2011

Photo update - tiling, vanities, benchtops and sink, go go go Eden Brae!

We met our SS on site on Friday, to discuss what is still left to be done. He is hoping by the end of next week he can schedule all remaining jobs and set our PCI date.

He will not guarantee that we'll be in by Christmas, but we are one of the close to completion that may just get there (please Angels, please!)

The error made with our skirting and architraves will now be left as is, we have decided it is not worth the delay to the build and given that we are so close, I will just have to grit my teeth and bare it in order to keep the work going!

Here are some photos taken on Friday during our visit:

My undermount kitchen sinks



Kitchen



Ensuite bath and niche


Ensuite shower


Ensuite vanity


Main bathroom


Main bathroom shower



View from our main bedroom (as taken by our 5 year old daughter) so a short person's view towards The Ponds


Skylight installed


Staircase installed