Initial Deposit 7/09/2010
Soil Report 29/09/2010
Contour Survey 5/10/2010
Tender Appointment 17/12/2010
Tender Signed 21/02/2011
Building Contract Appointment 4/03/2011
Building Contract Signed 8/03/2011
Permit Ordered 29/03/2011
Permit Received 6/05/2011
Colour Selection 25/03/2011
Electrical Selection 20/04/2011
Kitchen Upgrades 12/04/2011
Water Board Approval 17/03/2011
BASIX Approval 16/03/2011
Construction Certificate 6/05/2011
Engineering Drawings Signed 25/03/2011
Finance Approval 12/05/2011
Land Settlement 17/12/2010
Construction Drawings Signed 24/05/2011
Survey request ordered on Friday 20 May 2011, still waiting to see some pegs on our block, fingers crossed this happens early next week.