Saturday 28 May 2011

Our journey so far.....

Here is where our build is at:

     Initial Deposit   7/09/2010
     Soil Report    29/09/2010    
     Contour Survey   5/10/2010 
     Tender Appointment   17/12/2010    
     Tender Signed   21/02/2011    
     Building Contract Appointment   4/03/2011    
     Building Contract Signed   8/03/2011    
     Permit Ordered   29/03/2011    
     Permit Received   6/05/2011    
     Colour Selection   25/03/2011    
     Electrical Selection   20/04/2011     
     Kitchen Upgrades   12/04/2011    
     Water Board Approval   17/03/2011    
     BASIX Approval   16/03/2011    
     Construction Certificate   6/05/2011    
     Engineering Drawings Signed   25/03/2011    
     Finance Approval   12/05/2011    
     Land Settlement   17/12/2010    
     Construction Drawings Signed   24/05/2011   
Survey request ordered on Friday 20 May 2011, still waiting to see some pegs on our block, fingers crossed this happens early next week.

No comments:

Post a Comment